DNV Offshore Containers

We design and engineer offshore containers, modules and the lifting equipment that goes with them — to DNV 2.7-1, DNV 2.7-2, DNV 2.7-3, EN 12079 and ISO 10855. This page is the front door to everything we have written about the subject: the standards, the certification path, the design decisions that drive cost, and the tools you can use right now.

What counts as an offshore container

An offshore container is a portable unit that is lifted onto and off an offshore installation — a rig, a platform, a drill ship or a wind turbine foundation. It carries cargo, tools, chemicals, drilling waste or equipment, and it is lifted by crane while people are nearby. That last point is why the rules exist and why the paperwork is heavier than for a freight container.

Three things separate it from an ISO freight container: the lifting points are designed and certified for repeated offshore lifts, the structure is designed for a defined set of load cases including dynamic amplification, and the unit carries a certification file that a surveyor can check at any point in its life.

Typical sizes and certification levels

The table below shows the offshore container footprints we work with most often, the typical maximum gross mass we design and certify to, and the standard that applies to each unit type.

Unit type Footprint (approx.) Typical max gross mass Standard
10 ft container / basket 3.0 m × 2.4 m 9–12 t DNV 2.7-1 · EN 12079 · ISO 10855
20 ft container / basket 6.1 m × 2.4 m 18–25 t DNV 2.7-1 · EN 12079 · ISO 10855
30 ft container / basket 9.1 m × 2.4 m 27–32 t DNV 2.7-3 (DNV-ST-E273)
Service container (workshop, laboratory, accommodation) 10–30 ft shell per service function DNV 2.7-2 (DNV-ST-E272)
Portable offshore unit / equipment module project-specific project-specific DNV 2.7-3 (DNV-ST-E273)

Maximum gross mass is set at design and marked on the unit’s nameplate — it depends on the structure, materials and lifting arrangement, not on the footprint alone. Two containers with the same external dimensions can carry very different loads. What matters for certification is that the design load cases, the lifting arrangement and the marked gross mass are all consistent with each other and with the standard you are working to.

Which standard applies to your unit

This is the question that causes most delay on a project, because several standards overlap and class societies accept more than one route. In practice:

  • DNV 2.7-1 — the standard most offshore containers are built to: cargo containers and baskets for the offshore and petroleum industry.
  • DNV 2.7-2 — offshore service containers, where the unit carries equipment or a workshop rather than loose cargo.
  • DNV 2.7-3 — portable offshore units (POUs), the family used for pressurised and specialised units.
  • EN 12079 — the European offshore container standard, often required alongside DNV for North Sea work.
  • ISO 10855 — the international offshore container standard, increasingly specified where neither DNV nor EN is mandated.

The differences are not cosmetic: load cases, material requirements, testing and inspection intervals all change. If you are unsure which one your unit must meet, start with DNV offshore containers: regulations and standards, then read DNV 2.7-1 vs 2.7-2 vs 2.7-3 or ISO vs DNV offshore containers.

The certification path, step by step

  1. Design appraisal. The calculations and drawings go to the class society before anything is cut. Load cases, lifting points, materials and welding details are reviewed here. This is where most rework happens, and where a pre-submission check pays for itself.
  2. Fabrication survey. The surveyor witnesses material identification and the welds that matter — typically the lifting structure — against the approved drawings.
  3. Testing. Proof load and, where required, functional testing of the lifting set. Records become part of the certification file.
  4. Marking and certification. The unit is marked and the certificate issued, naming the maximum gross weight and the load cases it is approved for.
  5. Periodic inspection. From then on the unit is examined at defined intervals, and any modification or repair that affects the structure triggers reassessment.

Suggestion: the inspection checklist we use before submission.

Design decisions that drive cost and schedule

  • Load case selection. Designing for the wrong case is either unsafe or needlessly heavy. The three load cases of DNV 2.7-1 explain what each one governs.
  • Lifting and sling geometry. Dynamic amplification and sling angle set the load a pad eye actually sees. Use the pad eye and sling load calculator rather than estimating.
  • Materials and design temperature. Steel grade and toughness follow the design temperature — see material selection for offshore containers.
  • Bespoke versus standard. A modified catalogue unit is often cheaper than a clean sheet design, but only if the modification itself is certifiable.

Inspection, recertification and modification

A certified container is not certified forever. Recertification is triggered by the inspection interval, by damage, or by any modification — and the last of those is where projects come unstuck, because a change that looks trivial can alter the load path. Read what triggers recertification before you cut anything.

Buy, rent, or refit

New DNV 2.7-1 units run roughly $12,000–15,000; monthly rental is $400–600. Whether that favours buying depends on utilisation, contract length and how long you can wait for fabrication — the break-even is worked through in rent vs buy: the real cost. If you are sourcing rather than buying, read where to buy DNV-certified offshore containers first — the certificate, not the price, is what you should be comparing.

Free tools

Where to start reading

How we can help

We prepare certification packages that survive design appraisal, assess whether an existing unit can be modified rather than replaced, and design bespoke containers where the catalogue does not fit. Read the offshore container case study (PDF) for a worked example, or send us the specification and the standard you are working to — we will tell you what the certification will require before you commit to fabrication.