Engineering and Project Management
 

What the DNV 2.7-1 Standard Actually Requires: A Designer’s Checklist

This article is a structured walkthrough of DNV-ST-E271 (DNV 2.7-1) requirements, organised the way a designer or certification engineer actually works through them — from initial structural design through to the identification plate. Each section maps to a checklist you can use during design, procurement, and fabrication. It is not a substitute for reading the standard. But it tells you what to look for before you open it.

What DNV 2.7-1 actually is

DNV-ST-E271 (Offshore Containers, formerly DNV 2.7-1) is a certification standard — not a standalone design code. It specifies the requirements an offshore container must meet, the verification process for confirming compliance, and the documentation that must be produced and retained. It does not prescribe a single structural calculation method. Instead, it defines acceptance criteria and requires the designer to demonstrate compliance against those criteria using recognised engineering codes.

The practical consequence: DNV 2.7-1 gives you the freedom to use AISC, Eurocode, or API structural design methods — as long as the end result meets the acceptance criteria. Many designers new to DNV 2.7-1 find this uncomfortable. The standard does not hand you a formula. It hands you a performance requirement and says: prove it.

ℹ Key concept: design appraisal vs prototype testing

DNV 2.7-1 separates compliance verification into two stages.Design appraisal — where DNV reviews your calculations, drawings, and material specifications before fabrication begins. And prototype testing — where a physical unit is tested to verify the design actually performs. Both must pass. You cannot substitute one for the other.

Scope and applicability

DNV 2.7-1 applies to offshore containers with a Maximum Gross Weight (MGW) below 25,000 kg, designed for lifting and transport between vessels and offshore installations. It covers:

  • Standard offshore cargo containers (10ft, 20ft, 30ft)
  • Mud skips and bulk mud containers
  • Chemical drums and bulk chemical containers
  • Tool boxes and equipment containers
  • Offshore baskets (though DNV 2.7-2 is often used for lighter baskets)

It does not cover: service modules with active equipment (DNV 2.7-3), pressurised tanks to DOT/ADR specification (separate standards), or containers with MGW above 25,000 kg (DNV 2.7-3 territory).

⚠ MGW boundary is a hard limit

The25,000 kg MGW limit in DNV 2.7-1 is not a guideline. If your container, when loaded to its Safe Working Load, exceeds 25,000 kg MGW, DNV 2.7-1 does not apply — regardless of content type or configuration. You must certify under DNV 2.7-3. This catches out designers who add equipment or change payload assumptions mid-design.

Load cases the designer must account for

Before starting structural calculations, the load case matrix must be defined. DNV 2.7-1 requires the following load cases to be considered:

  • Dead weight — tare weight of the empty container plus structural steel weight
  • Payload (SWL) — the Safe Working Load, representing the maximum cargo weight the container is rated to carry
  • Vertical lifting loads — twice the SWL plus tare weight, applied at the centre of gravity of the container in a vertical lift (this is the proof load test load)
  • Eccentric lifting loads — the same vertical load applied at the extreme edge of the container's footprint, representing the worst-case lift with the load shifted to one corner
  • Stacking loads — the container stacked under others on a vessel deck, accounting for dynamic vessel motion; typically a stack factor of 1.5–2.0 × payload applied simultaneously with compressive and bending loads
  • Fork-lift loads — for containers designed to be fork-lifted, transverse point loads applied at the fork tunnels under the floor
  • Impact loads — for bottom-impact scenarios during landing on uneven surfaces; DNV 2.7-1 specifies a defined impact load case for base impact
  • Sea transport loads — dynamic accelerations in six degrees of freedom during vessel transport; typically derived from NOAA or DNV-specified sea state data for the intended operating area

The designer must demonstrate that the combined stress under all applicable load case combinations remains within the specified acceptance criteria — typically using a yield criterion (e.g., von Mises stress below yield strength with an appropriate safety factor) and a buckling check where compression dominates.

Structural frame requirements

01

Structural Design — Frame and Core

Structural calculations coverall applicable load cases: dead weight, SWL payload, vertical lift, eccentric lift, stacking, fork-lift, impact, and sea transport
Required
Yield check performed under all load case combinations; acceptance criterion: von Mises stress ≤ allowable yield with safety factor
Required
Buckling check performed on compression members under combined axial and bending loads
Required
Corner casting design verified fortwice SWL vertical lift without exceeding allowable stress in the casting or the surrounding structure
Required
Lifting eye / pad-eye design verified; DNV specifies minimum eye geometry, cheek plate thickness, and weld geometry
Required
Floor design accounts for concentrated point loads from cargo under dynamic motion — not just uniform static load
Required
Base frame and fork-lift tunnel design verified for transverse fork-lift loads to DNV-specified magnitude
Required
Structural drawings showmaterial grades, section sizes, weld detail symbols, and all critical connection geometry
Required
Stiffener sizing and spacing documented; structural fire protection specified if required by the operating environment
Recommended
DNV design appraisalapproval letter obtained before fabrication commences — this is a gate, not a parallel activity
Required

Material specifications

DNV 2.7-1 is prescriptive about material traceability and grade approval. The designer must specify materials that meet DNV-approved grades and ensure full traceability back to the mill certificate for every structural member.

02

Materials — Grade, Traceability, and Certification

Structural steel grades are specified fromDNV-approved material standards; typical grades: S355, S420, or S460 to EN 10025 or equivalent; documentary evidence of grade required
Required
All primary structural members (corner posts, base frame, roof frame) have mill certificates (EN 10204 3.1 or equivalent) traceable to heat number
Required
Fasteners (bolts, nuts, washers) aregrade-marked and certified; minimum grade specified in design; DNV may require specific fastener grades for lifting connections
Required
Lifting set components (shackles, swivels, wire rope or synthetic slings) are certified to recognised standards (e.g., EN 13411, ISO 7598) with current certificates
Required
Corner castings are DNV-type approved or certified to the applicable DNV acceptance standard; mill certificate required
Required
Pipe and plate for fluid-carrying components (mud skip internals, tank walls) are traceable to mill certificates and compatible with the fluid media
Required
Internal coating or lining material data sheets are compatible with the cargo media (OBM, WBM, brine, chemicals); certificate of compatibility available
Required
Material substitution during fabrication is not permitted without DNV-approved change order — this voids the design appraisal if not formalised
Required

Welding requirements

Welding is the most common source of non-conformance findings in DNV 2.7-1 certification. The standard requires pre-qualified welding procedures, qualified welders, and documented quality control — not post-fabrication inspection as a catch-all.

03

Welding — Procedures, Qualifications, and Quality Control

Welding Procedure Specifications (WPS) are prepared for all primary structural joints — full penetration welds on corner posts, base frame connections, and roof frame joints
Required
Each WPS isqualified by Procedure Qualification Record (PQR) in accordance with the applicable code (ISO 15614-1 or AWS D1.1 for steel; ISO 15614-2 for aluminium where applicable)
Required
Welder performance qualifications (WPQ) are current for each welder assigned to primary structural welds; records retained and available for DNV surveyor review
Required
Weld maps are prepared showingjoint location, WPS number, and welder ID for every primary structural weld — this is the traceability document DNV will request
Required
Non-destructive testing (NDT) requirements are defined for full penetration welds on primary structural joints; MT or UT required on selected joints per the NDT plan; RT may be required for thicker sections
Required
Weld acceptance criteria are defined toISO 5817 or equivalent; visual inspection, dimensional checks, and NDT results documented
Required
Welders working on aluminium lifting set components are qualified for aluminium; separate WPS required for aluminium fillet and full penetration welds
Required
Post-weld heat treatment (PWHT) is specified where material thickness or grades require it; procedure and temperature records retained
Recommended
Weld repair procedure is documented and DNV-approved before any repair is carried out — not after
Required

Corrosion protection

Offshore containers operate in a marine environment that is simultaneously corrosive and mechanically demanding. DNV 2.7-1 requires the corrosion protection system to be designed for the specific environment — not specified generically.

04

Corrosion Protection — Surface Preparation and Coating

External surface preparation is specified tominimum Sa2½ (ISO 8501-1) for abrasive blast cleaning — the baseline for marine coating systems
Required
Internal surface preparation for fluid-carrying containers (mud skips, chemical tanks) is specified for the media compatibility: for OBM, typically solvent-free epoxy to minimum300μm DFT; verify with coating manufacturer
Required
Coating system is specified with dry film thickness (DFT) per coat, number of coats, and total DFT; documentation includes manufacturer's data sheet and reference to ISO 12944 environment classification
Required
Corner castings, pad-eyes, and lifting connections areindividually coated or galvanised after weld-installation to prevent crevice corrosion at connections
Required
Coating adhesion test (ISO2409 or cross-cut test) isperformed on sample areas during production; results documented
Required
Touch-up procedures fordamage during fabrication and transport are documented; touch-up coating system matches the original specification
Recommended
Anode specification forsacrificial cathodic protection (if applicable) is designed for the operating environment; calculation documented
Note

Lifting set design

The lifting set is the most safety-critical system on the container. DNV 2.7-1 has specific requirements for the design, materials, and testing of the lifting set — including slings, shackles, and attachment points.

05

Lifting Set — Sling, Shackle, and Attachment Design

Lifting set is designed for twice the SWL as the proof test load; all components in the lifting path (sling, shackle, pad-eye, corner casting) are verified to the same factor
Required
Sling length and included angle are calculated to ensureno point load on the corner casting exceeds its rated capacity; typical limit: included angle ≤60° for 4-point lift
Required
Shackle size and grade are specified withminimum MBL (Minimum Breaking Load) of 5× SWL; bow-type shackles are preferred for angular loading; certificate of conformance required
Required
Pad-eye and lifting lug design accounts forcombined bearing, shear, and bending in the plate and surrounding structure; finite element analysis or hand calculation acceptable
Required
Corner casting-to-structure welds arefull-strength welds with specified leg length; weld quality verified by visual inspection and NDT on sample
Required
Wire rope orsynthetic sling specifications include: MBL, SWL, Diameter, construction, and evidence of current certification from manufacturer
Required
Lifting set components areindividually tagged and recorded in the certification documentation; sling length, batch number, and certificate reference are traceable
Required
For mud skips: the lifting set is designed to remain accessible and inspectable during operation; rigging configuration is documented and understood by the crane operator
Recommended

Prototype testing

Design appraisal must be completed before prototype testing begins. DNV will not witness a prototype test for a design that has not yet been approved. The sequence is: design approval → prototype fabrication → prototype test witnessed by DNV surveyor.

06

Prototype Testing — DNV Witness Requirements

Proof load test — container loaded to twice the SWL, lifted vertically, and held for a minimum of 5 minutes; DNV surveyor witnesses; test report issued
Required
Eccentric load test — where specified by DNV for the design: load shifted to one corner to test the lifting path under asymmetric loading; surveyor witnesses
Required
Stacking test — container subjected to the design stack load (typically 1.5–2× SWL applied vertically); stacking configuration documented; surveyor witnesses
Required
Fork-lift test — for containers with fork-lift tunnels: transverse point load applied at the fork pocket locations; structural integrity confirmed post-test
Required
Impact test — base impact test to DNV-specified load case; simulates landing on uneven surface; documented with load cell or strain gauge measurement where required
Required
After all tests:post-test inspection by DNV surveyor; container must show no visible damage, permanent deformation, or structural failure; report issued under DNV stamp
Required
If prototype test fails: design modification, re-appraisal, and re-test required before any production units are certified; production cannot start on the basis of a failed prototype
Required
Production units arenot re-tested — the prototype test validates the design; production quality is assured by DNV fabrication surveillance, not by re-testing every unit
Note

Fabrication surveillance

DNV surveyors visit the fabrication facility during production to verify that the as-built container matches the approved design. This is not a quality audit — it is a compliance verification. The surveyor checks specific items and has the authority to halt production if non-conformances are found.

07

Fabrication Surveillance — DNV Surveyor Visits

DNV surveyor notified atstart of fabrication; initial visit scheduled to verify material certificates, WPS on file, and welder qualifications before welding begins
Required
Material certificates presented and cross-checked against design specifications; traceability from mill certificate to fabrication records confirmed
Required
Weldmap available and weld identity traceable to welder ID; surveyor spot-checks weld quality by visual inspection during fabrication
Required
Coating application is witnessed or inspected: surface profile checked (Rugotest or Profile Gauge), DFT measured (ISO2808), adhesion tested
Required
Lifting set components presented for inspection before installation; surveyor verifies certificates, tag numbers, and physical condition
Required
Non-conformances raised andclosed before proceeding; NCR register available for DNV review; open NCRs are a certification block
Required
Final inspection visit: identification plate fitted in presence of surveyor; plate data verified against certificate; certificate issued
Required

Identification plate and marking

The identification plate is the physical evidence of certification. Without it, the container is not DNV-certified — regardless of what the certificate document says. The plate must be permanently attached, clearly legible, and contain specific data.

08

Identification Plate and Marking

Identification plate is metal, permanently fixed (riveted or mechanically fastened — not adhesive); location on container door or end wall specified in design
Required
Plate shows: DNV logo, container ID, SWL, tare weight, MGW, year of manufacture, and DNV certificate number
Required
Maximum Gross Weight (MGW) is shown in kg and in tonnes; tare weight shown separately
Required
Container is permanently marked with container ID on the frame (typically stencil or weld-stamp on base frame rail) — not only on the plate
Required
SWL is stencilled on the container frame in addition to the plate; minimum character height specified in DNV 2.7-1
Required
Fork-lift pocket positions are permanently marked on the base frame if the container is fork-lifted
Required
Safety warning labels (crane lift symbol, fork-lift warning) aredisplayed where visible during handling operations
Recommended

Periodic inspection

DNV 2.7-1 certification is not a one-time event. The standard requires periodic in-service inspection throughout the container's operational life. This is frequently the most overlooked requirement in the chain — both by manufacturers who do not communicate it clearly to buyers, and by operators who do not have a system to track it.

09

Periodic Inspection — In-Service Requirements

Periodic inspection interval is defined at certification; DNV 2.7-1 typically requires inspections at 2–5 year intervals depending on usage and operator requirements
Required
Inspection scope includes: visual inspection of lifting set, corner castings, frame, floor, and coating condition; lifting set NDT on critical components where corrosion or wear is suspected
Required
Inspection is conducted byDNV or DNV-approved surveyor; certificate of periodic inspection issued upon satisfactory completion
Required
Inspection records are retained for the life of the container + minimum3 years after decommissioning; available for operator and insurer review
Required
Operator has a tracking system for periodic inspection dates; containers with lapsed inspection are grounded until re-inspection is completed
Required
Damage identified during inspection isreported to DNV; repairs require DNV approval before the container is returned to service
Required
Any modification to a certified container — structural change, equipment addition, coating change — voids the certificate and requires re-certification
Required

"DNV 2.7-1 certification is a chain of documents: design calcs, material certs, WPS, PQR, WPQ, weldmap, NDT records, prototype test report, surveyor visit reports, and the certificate itself. Each link must be intact. Missing one is not a minor issue — it is a break in the compliance chain."

The complete checklist: summary table

For quick reference during design review or procurement, the table below maps each DNV 2.7-1 requirement to its phase in the project lifecycle.

Requirement Phase Status
Load case matrix defined and documented Design — upfront Required
Structural calculations (yield + buckling) Design — upfront Required
DNV design appraisal approval obtained Design — gate Required
Material certificates (EN 10204 3.1) for all structural members Procurement Required
WPS and PQR for all primary structural welds Procurement / Pre-fab Required
Welder WPQ records current Pre-fab Required
Weldmap prepared and traceable Pre-fab Required
NDT plan defined for primary structural welds Pre-fab Required
Corrosion protection system specified (internal + external) Design Required
Lifting set components certified (shackles, slings, castings) Procurement Required
DNV surveyor notified at start of fabrication Fabrication Required
Fabrication surveillance visits completed and NCRs closed Fabrication Required
Prototype testing witnessed by DNV surveyor Testing Required
Identification plate fitted under DNV witness Final inspection Required
Certificate issued by DNV Final inspection Required
Periodic inspection scheduled and tracked In-service Required
Modification control process in place In-service Required

Most common non-conformances in DNV 2.7-1 certification

Based on the patterns seen across certification projects, these are the issues that most frequently cause delays, re-work, or failed prototype tests:

  • Incomplete load case coverage — designers who account for vertical lifting loads but forget sea transport accelerations or eccentric lift; DNV will catch it at design appraisal, but the fix takes time
  • Unqualified welders on primary structural welds — WPQ records not current or not covering the specific WPS being used; easy to prevent, hard to fix after the fact
  • Coating specification mismatch — specifying a generic marine coating without confirming media compatibility for the specific cargo (OBM, chemical, brine); requires a full re-coat
  • Material substitution without change order — swapping S355 for S420 mid-fabrication without DNV approval; voids the design appraisal
  • Missing lifting set component certificates — slings or shackles purchased with certificates that do not cover the specific batch being used; DNV will not accept supplier declarations without batch traceability
  • Failing to notify DNV before fabrication starts — fabrication beginning before the design appraisal is approved; DNV may require hold points to be placed retroactively
✖ The prototype test failure scenario

The worst-case outcome: a container is fabricated, arrives on site, and the prototype test fails because the floor design did not account for the dynamic fluid load case. The container must be repaired or rebuilt, re-presented to DNV, and re-tested. The project delay cost typically far exceeds the original certification cost. This is entirely preventable with a complete load case matrix reviewed by DNV before fabrication.

How to use this checklist

This checklist is designed to be used at three stages:

  • Design phase — use it to verify your design package is complete before submitting to DNV for design appraisal; missing items here will surface as information requests that delay approval
  • Procurement phase — use it to verify supplier documentation against the requirements; material certs, WPS, WPQ, and component certificates must be in hand before fabrication starts
  • Fabrication phase — use it to track surveillance visit readiness; knowing which items the DNV surveyor will check at each visit allows the manufacturer to prepare and close non-conformances before the visit, not during it

Print it, put it in your project quality plan, and treat every Required item as a gate. The cost of catching a non-conformance at the checklist stage is a fraction of the cost of catching it at prototype test — or worse, after the container is on a vessel bound for an offshore installation.

DNV 2.7-1 DNV-ST-E271 Designer Checklist Offshore Containers Structural Design Welding Procedures Prototype Testing Periodic Inspection Mud Skips Chemical Tanks Fabrication Surveillance Lifting Set

Need a DNV design appraisal review before fabrication?

We support structural designers and manufacturers through the DNV 2.7-1 design appraisal process — from load case definition through to prototype test witness. Contact us to discuss your project scope.

© 2024 Certification Insight DNV 2.7-1 · Designer Checklist · DNV-ST-E271 · Offshore Container Certification
Project reference: Design of offshore containers, compliant with DNV 2.7-1, for well service applications

Share your project requirements below. We’ll review your specifications and respond with a detailed engineering proposal.